BIKE Beskids II

1 Stage

Earthworks, substructure, lean concrete, horizontal slab insulation, underfloor drains, garage hall reinforced concrete slab

1

2 Stage

Construction of the foundation walls of the garage hall

2

3 Stage

Construction of ceiling over garage, hydro vertical insulation of garage without insulation

3

4 Stage

Construction of load-bearing walls of the first floor. Excavation of the ceiling above the first floor. Construction of load-bearing walls on the second floor

4

5 Stage

Construction of the ceiling over the 3rd floor. Construction of load-bearing walls on the 4th floor. Construction of the roof structure

5

6 Stage

Delivery of window frames for the first floor and 1st floor. Installation of electrical and plumbing on the first floor and 1st floor

6

7 Stage

Delivery of window frames for the 2nd and 3rd floors. Installation of electrical and plumbing on the 2nd and 3rd floors

7

8 Stage

Interior plastering on the first floor and 1st floor. Implementation of 50% of the roofing. Implementation of thermal insulation of the facade of the western part.

8

9 Stage

Performing plastering on the 2nd and 3rd floors. Implementation of 50% of the roofing. Implementation of thermal insulation of the facade eastern part

9

10 Stage

Performing screeds 3rd and 2nd floor. Implementation of thermal insulation of the facade northern part

10

11 Stage

Performing screeds on the 1st floor and first floor. Implementation of thermal insulation of the facade south part. Finishing works of premises inside

11

12 Stage

Elevator installation. Interior finishes continue.

12

13 Stage

Construction of common areas on the 1st floor and first floor. Continuation of finishing work on the apartments inside. Construction of parking areas, green areas, access roads, finishing work on the exterior of the building.

13